DDMRP: definition, buffers, difference from MRP, software and implementation

Published on November 8, 2026

DDMRP (Demand Driven Material Requirements Planning) is a planning and execution method that places stock buffers at a few chosen points in the chain, then triggers replenishment according to the actual consumption of these buffers rather than the forecast. It complements MRP, it does not replace it. It targets plants whose customers wait less than the cumulative manufacturing and purchasing lead time.

Where DDMRP comes from

  • The authors. Carol Ptak and Chad Smith introduced the method in the third edition of Orlicky's Material Requirements Planning (McGraw Hill, 2011).
  • The institute. The same year they founded the Demand Driven Institute, which trains, certifies and checks software compliance.
  • The reference book. Demand Driven Material Requirements Planning, Version 3 (Industrial Press, 2019).
  • The roots of the method. According to the Demand Driven Institute, DDMRP combines the still relevant parts of MRP and DRP, the pull and visibility emphasis of Lean and the Theory of Constraints, and the variability reduction of Six Sigma.

DDMRP vs MRP: the difference

MRP calculates, from forecasts and bills of materials, what to buy and make, how much and when. When demand varies, each deviation spreads through every level of the bill of materials. DDMRP stops this spread with decoupling points.

  • The driver. MRP: the forecast and the sales and operations plan, in push mode. DDMRP: actual consumption, in pull mode, according to SAP's comparison table.
  • The environment. SAP assigns MRP to stable, predictable demand, and DDMRP to a volatile environment.
  • The items. Only strategic items are managed with buffers. MRP keeps planning the others.
  • Priority. MRP prioritises by due date. DDMRP prioritises by buffer level: the lower the buffer, the more urgent the order.

SAP presents DDMRP as an optional extension of MRP and adds that, for many manufacturers, MRP is enough.

The six components of DDMRP

The Demand Driven Institute now describes six components. The first three configure the model, the fourth and fifth run it, the sixth readjusts it.

  • Strategic decoupling. You choose where to place the stock buffers. This choice sets the lead time promised to the customer and the money tied up in inventory. The Demand Driven Institute uses six criteria to place these points.
  • Buffer profiles and levels. Items with similar characteristics (lead time, bill of materials level, variability) share a profile of settings.
  • Dynamic buffer adjustments. Buffers move up or down with consumption, lead times and planned events, such as a promotion or a season.
  • Demand driven planning. A calculation rule, the net flow equation, generates orders, usually at least once a day.
  • Visible and collaborative execution. Open orders are tracked with buffer status alerts and synchronisation alerts.
  • Tactical adaptation. The model is reviewed against its past results and planned activity: this is DDS&OP, demand driven sales and operations planning. According to the Demand Driven Institute, it no longer uses a master production schedule (MPS).

SAP sums up the method in three words: position, protect, pull.

DDMRP buffer zones

Each buffer has three colour zones, described in the Microsoft Dynamics 365 documentation:

  • The red zone, below the minimum level, is the safety zone. Stock should not fall into it.
  • The yellow zone, between the minimum and the reorder point, covers consumption during the replenishment lead time.
  • The green zone, between the reorder point and the maximum, sets the frequency and size of orders.

The formulas given by Microsoft:

  • Yellow zone = average daily usage × decoupled lead time.
  • Red zone = average daily usage × decoupled lead time × lead time factor, plus that same amount × variability factor.
  • Green zone = the largest of three values: minimum order quantity, average daily usage × order cycle, average daily usage × decoupled lead time × lead time factor.

The decoupled lead time is the time to make or buy an item when the upstream decoupling points are in stock; it is usually much shorter than the cumulative lead time. Microsoft cites the ranges recommended by the Demand Driven Institute: lead time factor of 0.20 to 0.40 for a long lead time, 0.61 to 1 for a short one; variability factor of 0.20 to 0.40 for low variability, 0.61 to 1 for high variability.

The net flow equation, with an example

Net flow is on-hand stock, plus open orders, minus qualified demand. Qualified demand is past-due demand, plus today's demand, plus significant upcoming order spikes. When net flow reaches the top of the yellow zone or falls below it, you order the difference between the top of the green zone and the net flow.

Calculation example, with values chosen for illustration:

  • Average usage of 40 parts per day, decoupled lead time of 5 days, lead time and variability factors of 0.5, order cycle of 7 days, minimum order quantity of 200 parts.
  • Yellow zone: 40 × 5 = 200. Red zone: 100 + 50 = 150. Green zone: the largest of 200, 280 and 100, i.e. 280.
  • Top of red at 150, top of yellow at 350, top of green at 630.
  • On-hand stock of 180, open orders of 120, qualified demand of 40: net flow of 260, in the yellow zone.
  • Proposed order: 630 minus 260, i.e. 370 parts.

Industrial example: Michelin

In a Techniques de l'Ingénieur publication on the move from DDMRP to the Demand Driven Adaptive Enterprise model (DDAE), published on 10/01/2023, Thibaut d'Herouville, Supply Chain Industry Director of the Michelin group, wrote the chapter on Michelin's project. He describes an eight-level chain, from material suppliers to retailers, about 15,000 items, 200 materials in a tyre and inventories in the order of 4 billion euros.

DDMRP software

DDMRP is used either within the ERP, or in a supply chain planning tool connected to the ERP. SAP considers its ERP module sufficient for most small and medium-sized companies, and points groups with several divisions towards its planning tool. The Demand Driven Institute publishes the list of software that has passed its compliance check (viewed on 08/11/2026), including:

  • ERP: SAP S/4HANA, SAP Integrated Business Planning for Demand-Driven Replenishment, Microsoft Dynamics 365 Supply Chain Management, IFS Applications.
  • Add-on tools: Intuiflow (Algo), B2Wise, DELMIA Supply Chain Planning and Optimization (Dassault Systèmes), DSCP (QAD DynaSys), OMP, Blue Yonder, Anaplan, Service Optimizer 99+ (ToolsGroup), Simio RPS, and two French vendors, MyDDMRP (Applidev) and Smart Reassort (IngenCys).

The institute states that compliance covers the software, not the vendor's ability to make the method work, and that it assumes trained teams. Elisa Industriq, an exhibitor at Tech for Industry Show 2027, offers DDMRP within its planning suite, alongside sales forecasting, inventory management and scheduling (see the exhibitor). To compare planning tools, see our guide on supply chain software.

Implementing DDMRP

  • Check that the case fits. The Demand Driven Institute targets variable environments where the lead time accepted by the customer is much shorter than the cumulative lead time. It adds that the method is not a silver bullet.
  • Choose the decoupling points in the bills of materials and the chain, before any calculation.
  • Clean the data: usage, lead times, minimum quantities, bills of materials.
  • Set up profiles and buffers, then let them adjust.
  • Train the teams. AfrSCM, the French supply chain association, offers the Demand Driven Institute's Adaptive Enterprise Foundations Professional certification: two days of training in French, exam in English, next session on 18 and 19/02/2027 in Paris, 1,400 euros excluding VAT for members and 1,600 euros for non-members (page viewed on 08/11/2026).
  • Link DDMRP to S&OP through a regular review of the settings (DDS&OP).

DDMRP acts on one specific level of production planning, the requirements calculation.

What manufacturers said at Tech for Industry Show

At Tech for Industry Show 2026, No Chain Technologies and the consultancy Argon & Co described the limits that DDMRP also seeks to address. In their view, MRP, 60 to 70 years old, plans sequentially and lacks visibility on priorities at the upstream levels of the bill of materials. For complex products, about 65% of service problems come from suppliers, and the "last missing part" can account for up to 40% of total inventory in aerospace, defence or rail. Their answer is different: a control tower that constantly compares what the plant must do with what it can do. Read the article

Frequently asked questions

What is DDMRP?

A planning and execution method that places stock buffers at chosen points in the chain and replenishes according to the actual consumption of these buffers.

What is the difference between DDMRP and MRP?

MRP is forecast driven and prioritises by date. DDMRP is driven by actual consumption and prioritises by buffer level. It complements MRP, which keeps planning non-strategic items.

What are the zones of a DDMRP buffer?

Red for safety, yellow for consumption during the replenishment lead time, green for the frequency and size of orders.

Which software supports DDMRP?

The Demand Driven Institute publishes the list of compliant software: ERPs such as SAP S/4HANA, Microsoft Dynamics 365 or IFS, and add-on tools such as Intuiflow, OMP or DELMIA.

How can I get trained in DDMRP?

Through the Demand Driven Institute certifications, offered in France by AfrSCM among others.