Industrial waste heat in France: definition, potential, recovery options, obligations and Fonds Chaleur funding

Published on November 25, 2026

Industrial waste heat is heat produced by a process whose main purpose is not to produce energy: furnace flue gases, cooling water, refrigeration units, compressed air. It is usually discharged without being used, even though it could heat another process on the site, a neighbouring company or a district heating network. ADEME, the French ecological transition agency, puts the French potential at 109.5 TWh, and two texts already require manufacturers to study it: the cost-benefit analysis for installations above 20 MW, and the energy audit since 2025.

Definition: what waste heat covers

The French Ministry for the Ecological Transition defines recovered heat, or waste heat, as heat generated by a process whose primary purpose is not energy production, and which is therefore not necessarily recovered. Recovering it means capturing this heat and carrying it to a thermal use.

The sources listed by the ministry are varied:

  • industrial production sites, for example the heat in furnace flue gases or in manufactured products as they cool down;
  • service-sector buildings that use a lot of heat, such as hospitals;
  • data centres;
  • waste-to-energy plants and incinerators for non-household waste.

In a plant, the sources are found wherever energy comes in as heat and leaves at a temperature that is still useful: furnaces, boilers, dryers, distillation columns, refrigeration units, compressors.

The potential in France

According to the ministry, an ADEME study carried out in 2015 and updated in 2017 puts the waste heat potential in France at 109.5 TWh, including incinerators, wastewater treatment plants and data centres. The potential located near existing heating networks is about 16.7 TWh above 60 °C.

The share actually recovered remains small. The ministry relies on the annual survey of heating networks: in 2016, these networks carried 525 GWh of recovered industrial heat, against 9.3 TWh from waste-to-energy plants. These figures are old, but they are the latest the ministry has published on the subject.

Four ways to use waste heat

The ministry distinguishes four outlets, from the most direct to the most distant:

  • On the site itself, for its own needs: drying, process preheating, space heating. This is the simplest outlet, because the heat does not leave the plant.
  • At a neighbouring company, through a network between two sites.
  • In a district heating network, which supplies housing and public buildings.
  • To produce electricity. The ministry points out that converting heat into electricity is less efficient than using the heat directly, and that the French Energy Code provides no support for this route. It can make sense if there is no heat outlet nearby.

The equipment is what ADEME's Fonds Chaleur (heat fund) lists in its scope:

  • heat capture on a process: distillation column, dryer, furnace, boiler;
  • temperature upgrading with a heat pump, when the recovered heat is too cold for the intended use;
  • cooling production from heat, with an absorption chiller or a heat pump set up to produce heating and cooling at the same time;
  • transport and distribution: pipework, ducts, heat exchangers, internal water loop, network to a neighbouring manufacturer or connection to a district heating network.

The first task is to know your discharges: their temperature, flow rate and timing, compared with the site's heat needs. Heat available at night does not serve a process that runs during the day unless it is stored. This is a measurement matter, covered by industrial data: energy meters, temperature sensors and historising alongside production data.

What the regulations require

Cost-benefit analysis above 20 MW

The French order of 09/12/2014, amended by the order of 03/08/2018, requires a cost-benefit analysis to assess the value of recovering waste heat through a heating or cooling network. It covers two categories of classified installations subject to authorisation or registration:

  • installations with a total rated thermal input above 20 MW that generate unrecovered waste heat;
  • energy production installations above 20 MW that are part of a heating or cooling network.

The analysis is part of the authorisation or registration file. It applies to a new installation, or to an installation undergoing a substantial modification and a refurbishment costing more than 50% of a comparable new thermal unit.

Article 3 of the order exempts electricity generation installations, and those that meet one of these conditions:

  • an unrecovered waste heat discharge below 80 °C;
  • a discharge below 10 GWh per year;
  • a heat demand located more than 4 km from an installation discharging less than 50 GWh per year, more than 12 km for less than 250 GWh per year, or more than 40 km above 250 GWh per year.

If the analysis shows that the benefits exceed the costs, and no overriding legal, ownership or financial reason prevents it, the operator implements the recovery solution (article 5).

The 2025 energy audit

Since the French law of 30/04/2025, the energy audit is mandatory for companies that use 2.75 GWh of final energy per year or more; our article on the industrial energy audit details the thresholds and deadlines. The order of 10/07/2025, which sets the audit method, makes it a tool for identifying waste heat. For industrial processes, the audit characterises the consumption and temperature levels of heat-consuming processes, and it assesses the temperatures of waste heat discharges. It also assesses opportunities to use renewable and recovered energy.

The proposed actions are sorted into four payback categories: one year or less, one to three years, three to five years, more than five years. A heat recovery project identified by the audit therefore goes into the company's action plan.

Funding a project: the Fonds Chaleur and CEE

ADEME's Fonds Chaleur has supported waste heat recovery since 2015. According to the ministry, 74 installations had received support at the date of the last update of its page, 23/08/2018, for nearly €23 million of aid and output of 100 ktoe per year.

The conditions of the aid, read on ADEME's page on 25/11/2026:

  • recovered heat above 1 GWh per year in mainland France;
  • a minimum energy and environmental performance threshold;
  • a simple payback period above 3 years;
  • a prior study: an energy audit or a study of the energy mix, supplemented by a feasibility study, to check that the project is consistent with the site's decarbonization roadmap.

Since 2020, ADEME's aid has been coordinated with French energy savings certificates (CEE), under terms set out in its eligibility conditions.

Point to note: ADEME's page states that new applications to the Fonds Chaleur are suspended, because of the number of projects waiting. The 2026 call is shown as closed, open from 01/01/2026 to 04/11/2026. ADEME states that the applications submitted represent €1.8 billion before review, against a provisional budget of €500 million in 2027. A waste heat recovery project should therefore be prepared now, feasibility study included, so that it is ready when applications reopen, while also looking at CEE funding.

What manufacturers said at Tech for Industry Show

At Tech for Industry Show 2026, Olivier Sala (ENGIE) devoted his keynote to the energy challenges of industrial transformation. He pointed out that heat accounts for about half of the energy used by European industry and that less than 10% of it is electrified. He added that below 200 °C heat pumps work fairly easily, and he recommends hybridising boilers with heat pumps, with a payback of around 3 to 4 years. Read the article

Among the exhibitors of the 2027 edition, Optimistik publishes OIAnalytics, an industrial data platform that tracks the energy efficiency of plants, among other things, and CertiNergy & Solutions helps finance energy performance projects through French energy savings certificates (CEE).

Frequently asked questions

What is industrial waste heat?

Heat produced by an industrial process whose main purpose is not to produce energy, and which is usually discharged without being used.

How much waste heat is there in France?

109.5 TWh according to the ADEME study updated in 2017, cited by the ministry, including about 16.7 TWh above 60 °C near existing heating networks.

How can waste heat be used?

On the site, at a neighbouring company, in a district heating network or, if there is no outlet, to produce electricity.

Who must carry out a cost-benefit analysis?

Classified installations above 20 MW that generate unrecovered waste heat, unless exempt: discharge below 80 °C, discharge below 10 GWh per year or heat demand too far away.

Does the energy audit cover waste heat?

Yes: since the order of 10/07/2025, the audit of industrial processes assesses the temperatures of waste heat discharges.

Does the Fonds Chaleur still fund waste heat recovery?

The scheme exists, but new applications are suspended according to ADEME's page read on 25/11/2026.