A preventive maintenance plan lists, for each asset on a site, the tasks to carry out before failure, their interval, their duration, and the parts and skills required. It is built in six steps: inventory, criticality, failure modes, choice of tasks, intervals, then follow-up in a CMMS. In France, it must also include the periodic inspections required by regulations, for example every twelve months for electrical installations and lifting equipment.
Preventive maintenance: definition and types
The EN 13306:2017 standard, published in France as NF EN 13306 in November 2017 and in force, sets the vocabulary of maintenance. Preventive maintenance is carried out before failure, to reduce its probability; corrective maintenance is carried out after. Preventive maintenance falls into two families:
- Time-based (predetermined) preventive maintenance: the task is done at fixed intervals, in time (every month), in running hours or in number of cycles, without first checking the condition of the asset. Example: replacing a belt every 4,000 hours.
- Condition-based maintenance: the task is triggered by a measurement of the asset's condition (vibration, temperature, thickness, oil analysis) crossing a threshold.
- Predictive maintenance is condition-based maintenance that extrapolates the trend of the measurement to forecast when to intervene. It is the field of predictive maintenance programmes.
A plan and a schedule are not the same thing: the plan says what to do, on which asset and at what interval; the schedule says when and by whom each task is done, week by week.
Building a preventive maintenance plan in 6 steps
- 1. List the assets. A site hierarchy (line, machine, subassembly, component), with for each asset its reference, manufacturer, manual and failure history.
- 2. Rank the assets by criticality. Effect of a stoppage on safety, the environment, quality, production and cost. A bottleneck asset or one without redundancy comes first. Low-criticality assets that are cheap and quick to replace can be left to run to failure: this is a choice, not an oversight.
- 3. List the failure modes of critical assets. Machine FMECA (AMDEC) is the tool: for each possible failure, its cause, effect, detection and criticality.
- 4. Choose the task for each failure mode. Time-based replacement when wear is steady and linked to use; condition monitoring when wear shows before failure; a regulatory inspection when the law requires it; a change to the equipment when no maintenance is enough.
- 5. Set the intervals. From the manufacturer's manual, regulations, failure history and the P-F interval rule for condition-based tasks (see below).
- 6. Load the plan into the CMMS and review it. Each task becomes a routine with its triggers, parts and duration; deviations and actual failures are used to correct the intervals, at least once a year.
Setting the right interval
- The manufacturer's manual gives the starting point: greasing, oil changes, replacement of wear parts, in running hours or cycles. It assumes normal operating conditions; three-shift operation, a dusty or hot environment justify shorter intervals.
- Failure history corrects this starting point. MTBF calculation per asset shows whether failures decrease once the plan is in place.
- The P-F interval, for condition-based tasks. It is the time between the moment a failure becomes detectable (P, potential failure) and the moment the asset no longer performs its function (F, functional failure). To catch the failure in time, inspections must be more frequent than this interval. Common reliability centred maintenance practice is to inspect at half the P-F interval, and more often when the stakes are high. Example: if rising vibration announces a bearing failure about eight weeks ahead, a measurement every four weeks is usually enough.
- Regulations set a ceiling, never a target: nothing prevents more frequent checks when the asset's condition calls for it.
Mandatory periodic inspections to include in the plan (France)
Several French labour and environmental regulations require inspections at set intervals. They belong in the plan, with their reference text and the name of the body or competent person who carries them out. Main inspections for a plant:
- Electrical installations: periodic inspection every year, starting from the initial inspection (article R4226-16 of the French Labour Code, order of 26/12/2011, article 3). The head of the establishment can extend the interval to two years if the previous report contains no observations, or if the non-conformities have been corrected, after informing the labour inspectorate.
- Lifting equipment: general periodic inspection every twelve months; every six months for forklift trucks, mobile elevating work platforms, mobile cranes and equipment that carries people or raises a workstation (order of 01/03/2004, article 23). Lifting accessories (slings, chains, lifting beams) are inspected every twelve months (article 24).
- Pressure equipment: periodic inspection at most every two years for steam generators and at most every four years for most other equipment; periodic requalification at most every ten years for most vessels, piping and steam generators, more often for toxic or corrosive fluids (order of 20/11/2017, articles 15 and 18). The operator shortens these periods if the condition of the equipment requires it.
- Automatic doors and gates: maintenance and inspection at least every six months, and after any failure, recorded in a maintenance log (order of 21/12/1993, article 9).
The complete list, including workplace conditions (noise, dust, gases), is kept up to date by INRS, the French occupational safety institute, in its brochure ED 828 "Principales vérifications périodiques", last published in September 2026.
Example: preventive maintenance plan for a centrifugal pump
A centrifugal pump feeds the cooling circuit of a press, in continuous operation. It is rated critical: if it stops, the press stops. Proposed plan:
- Every week (round, operator): visual check for leaks at the mechanical seal, abnormal noise, discharge pressure read on the gauge.
- Every four weeks (condition-based, technician): vibration and bearing temperature measurement, compared with alert thresholds; above the threshold, a work order to replace the bearings.
- According to the manufacturer's manual (time-based): bearing greasing at the stated number of running hours; coupling alignment check after any work on the motor or the pump.
- Every year (time-based, planned shutdown): inspection of impeller and volute wear, preventive replacement of the seal if the history shows leaks during the year.
- Critical spare parts in stock: one mechanical seal, one set of bearings, one coupling.
The intervals in this example are illustrative: each site sets them with its own pump's manual, operating conditions and history.
Preventive maintenance plan in Excel: useful columns
A spreadsheet is enough to start, for one workshop or line. Useful columns:
- Asset: code, description, location, criticality.
- Task: description of the work, failure mode targeted, type (time-based, condition-based, regulatory).
- Interval: value and unit (days, weeks, running hours, cycles), reference text for a mandatory inspection.
- Resources: trade or contractor, planned duration, production stoppage required or not, parts and tools.
- Follow-up: date last done, next due date calculated by formula, comments.
The limit comes quickly: a spreadsheet does not count running hours, does not trigger work orders, does not reserve parts and does not keep the history of interventions. That is the role of the cmms, which turns each line of the plan into a preventive routine based on calendar or meter readings.
What manufacturers said at Tech for Industry Show
At the 2026 show, Aymeric Renaud gave in his keynote the example of a plant in Normandy: on a machine from the 1980s, a bottleneck in contactor production, vibration and temperature sensors turned 4 hours of corrective maintenance into a 10-minute preventive intervention, with a payback of less than 6 months. Read the article
The Nerya speaker traced the evolution of industrial maintenance: first a "firefighting" mode, then the arrival of preventive maintenance, which brought in safety while reducing costs and incidents, then the spread of CMMS software. Read the article
Among the exhibitors of the 2027 edition, CARL Software, a subsidiary of Berger-Levrault, publishes maintenance and asset management software for industrial and commercial sites.
Frequently asked questions
What is a preventive maintenance plan?
The list of tasks to carry out on each asset before failure, with their interval, duration and required resources.
What are the types of preventive maintenance?
Time-based, at fixed intervals, and condition-based, triggered by a measurement of the asset's condition; predictive maintenance is condition-based maintenance that forecasts when to intervene.
What is the difference between a maintenance plan and a maintenance schedule?
The plan says what to do and how often; the schedule says when and by whom each task is done.
How do you set the interval of a preventive maintenance task?
With the manufacturer's manual, regulations, failure history and, for condition-based tasks, inspections more frequent than the P-F interval.
Which inspections are mandatory in a French plant?
Among others, electrical installations (every year), lifting equipment (every twelve or six months), pressure equipment (inspection at most every two or four years) and automatic doors (at least every six months). The INRS brochure ED 828 lists them.
Can you build a preventive maintenance plan in Excel?
Yes, to start, with one row per task; beyond a few dozen assets, a CMMS triggers the work and keeps the history.
Further reading
Our industrial maintenance page brings together the show's talks, articles and exhibitors on industrial maintenance and asset management.