Industrial heat pumps in France: how they work, temperatures, COP, CEE scheme IND-UT-137 and refrigerants

Published on November 26, 2026

An industrial heat pump takes low-temperature heat, most often the site's waste heat, and raises it to the temperature of a process using an electric compressor. It replaces all or part of a gas boiler and mainly serves needs below 200 °C. In France, the CEE scheme IND-UT-137 funds these installations up to 5 MW, subject to COP and refrigerant conditions, while ADEME's Fonds Chaleur has suspended new applications.

Principle: upgrading heat that is too cold to use

A vapour compression heat pump circulates a refrigerant in a closed loop. It evaporates by taking heat from a cold source, an electric compressor raises its pressure and temperature, then it releases this heat to the process as it condenses. The fluid then expands and the cycle starts again.

In a plant, the cold source is often waste heat: cooling water, dryer vapours, flue gases, the condenser of a refrigeration unit. Our article on industrial waste heat details these sources and the related obligations. The heat pump comes in when this heat is too cold to be reused as it is.

Its efficiency is measured by the COP, coefficient of performance: the heat delivered divided by the electricity consumed. The larger the temperature gap between the source and the need, the lower the COP.

What temperatures an industrial heat pump reaches

The International Institute of Refrigeration summarised the state of the art in a note published on 30/11/2021:

  • many industrial processes need heat between 80 °C and 300 °C, especially in food, beverages, chemicals and paper;
  • few vapour compression heat pumps deliver heat above 90 °C;
  • the achievable limit with this technology was 160 °C at the date of the note;
  • worldwide, 42% of industrial residual heat is available below 100 °C, which makes it a natural source for a heat pump.

A heat pump is called high-temperature when it goes beyond this threshold of about 90 to 100 °C. The CEE scheme IND-UT-137 sets two levels of requirement depending on whether water leaves the condenser at 100 °C or less, or above.

The potential in Europe

The study by Marina et al. (2021), reported by the International Institute of Refrigeration, estimates the market for industrial heat pumps up to 200 °C in the EU-28 at:

  • 23.0 GW of cumulative capacity, or 4,174 machines;
  • 641 PJ per year of process heat, 57% of the heat needs below 200 °C of the sectors studied;
  • a median COP of 2.77;
  • by sector: chemicals 9.1 GW, paper 7.9 GW, food 5.5 GW, refining 0.5 GW;
  • up to 52.6 Mt of CO2 avoided per year, in a scenario where electricity is fully decarbonized;
  • an investment estimated at between €4.6 and €11.5 billion.

Funding an industrial heat pump in France

CEE scheme IND-UT-137

The standardised operation sheet IND-UT-137, "Heat pump system raising the temperature of recovered waste heat", is published by the French Ministry for the Ecological Transition in a version applicable from 25/05/2026. Its main conditions:

  • sector: industry, for a heat need on the site (process, space heating, domestic hot water);
  • machine: vapour compression heat pump driven by an electric motor, with a heating capacity of 5 MW or less;
  • source: waste heat from a process on the same site, at 25 °C or more for at least 90 days per year, with an annual average above 18 °C; heat from closed-loop process cooling on the evaporator side of a refrigeration unit is not eligible;
  • refrigerant: a global warming potential below 150;
  • performance: a minimum annual average COP that depends on the temperature lift; for example 5.9 below 30 K, 4.4 at 40 K, 3.5 at 50 K, 3.0 at 60 K and 2.5 from 70 K for a condenser outlet at 100 °C or less; 4.5, 3.4, 2.7, 2.2 and 2.0 above 100 °C;
  • prior sizing study, dated and signed, with load curves for waste heat and needs, 5 to 10 operating points and the simultaneity between the two;
  • metering: wattmeters on compressors and auxiliaries, thermal energy meters on the condenser and evaporator, values kept for six years;
  • conventional lifetime: 14 years; operations committed before 01/01/2031.

The volume of certificates is 10.986 × (Q − Eelec), in kWh cumac, where Q is the heat delivered per year and Eelec the electricity absorbed per year. The required metering is the kind of energy monitoring found in the industrial energy audit, which also identifies waste heat discharges.

The Fonds Chaleur, suspended

ADEME's Fonds Chaleur includes "systems raising temperature via a heat pump" in the scope of its aid for waste heat recovery. Its conditions: more than 1 GWh of recovered heat per year in mainland France, a simple payback above 3 years and a prior study. But ADEME's page, read on 26/11/2026, states that new applications are suspended: the 2026 aid has been closed since 04/11/2026, and the applications submitted represent €1.8 billion against a provisional budget of €500 million in 2027. ADEME's aid has been coordinated with CEE since 2020.

Refrigerants: what the F-gas regulation requires

Regulation (EU) 2024/573 on fluorinated greenhouse gases gradually bans placing on the market heat pumps that use fluids with a high global warming potential (GWP). For stationary equipment, its Annex IV provides in particular:

  • monobloc and other self-contained heat pumps above 12 kW and up to 50 kW: banned with a refrigerant of GWP 150 or more from 01/01/2027;
  • other self-contained heat pumps: same threshold of 150 from 01/01/2030;
  • split systems above 12 kW: GWP of 750 or more banned from 01/01/2029, GWP of 150 or more from 01/01/2033;
  • a limit raised to 750 when the site's safety requirements do not allow a fluid below 150.

Since 01/01/2026, the regulation also bans the use of fluorinated gases with a GWP of 2,500 or more to service heat pumps, with a tolerance for reclaimed or recycled gases until 01/01/2032. A machine chosen today should therefore run on a refrigerant with a GWP below 150, the threshold that IND-UT-137 already requires.

Project steps

1. Measure heat discharges and needs: temperatures, flow rates, timing, over a representative year. Without historical data, the CEE scheme accepts a measurement campaign of at least two months.

2. Overlay the load curves to check that waste heat and demand occur at the same time, or plan for storage.

3. Calculate the temperature lift and the expected COP, then compare it with the minimum COP of the scheme.

4. Choose between full boiler replacement and a hybrid system.

5. Put the funding together: CEE, and the Fonds Chaleur when it reopens.

6. Install the meters at commissioning, to prove the savings.

What manufacturers said at Tech for Industry Show

At Tech for Industry Show 2026, Olivier Sala (ENGIE) pointed out that heat accounts for about half of the energy used by European industry, and that less than 10% of it is electrified. In his view, below 200 °C heat pumps work fairly easily, while above that it is less certain. He recommends hybridisation: installing a heat pump on 40 to 50% of a boiler's capacity, which costs less, and curtailing electricity consumption at certain times in exchange for payment. He cites a payback of around 3 to 4 years. Read the article

Among the exhibitors of the 2027 edition, CertiNergy & Solutions helps finance energy performance projects through French energy savings certificates (CEE), and Optimistik publishes OIAnalytics, an industrial data platform that tracks energy efficiency among other things, useful for measuring available heat and proving savings.

Frequently asked questions

What is an industrial heat pump?

A machine that takes low-temperature heat, often waste heat, and raises it to the temperature of a process using an electric compressor.

What temperature can an industrial heat pump reach?

According to the International Institute of Refrigeration, few vapour compression machines go above 90 °C, and the limit of this technology was 160 °C in 2021.

What is the COP?

The ratio between the heat delivered and the electricity consumed. It falls as the temperature gap between the source and the need increases.

Which CEE scheme applies to an industrial heat pump?

Scheme IND-UT-137, for an electric heat pump of 5 MW or less that upgrades the site's waste heat, with a refrigerant of GWP below 150 and a minimum annual COP.

Does the Fonds Chaleur still fund industrial heat pumps?

The scheme exists, but new applications are suspended according to ADEME's page read on 26/11/2026.

Which refrigerant should be chosen?

A refrigerant with a GWP below 150: this is the threshold of Regulation (EU) 2024/573 for most self-contained heat pumps from 2027 or 2030, and that of the CEE scheme.

Further reading

Our industrial decarbonization page brings together the show's talks, articles and exhibitors on energy efficiency and decarbonization.